ANDHRA PRADESH POWER GENERATION CORPORATION LIMITED
VIDYUT SOUDHA  ::  Vijayawada - 520004
Daywise Generation Particulars as on  :  18-01-2019
Station Unit Capacity Daywise generation in MU 1st to 18th Jan 1st Apr to 18th Jan
(MW) 16-01-19 17-01-19 18-01-19 Gen (MU) PLF (%) Gen (MU) PLF (%)
Thermal Power Stations                
Dr.Narla Tatarao Unit 1 210.0           754.29 51.08
(Vijayawada) Unit 2 210.0 3.71 3.71 4.00 71.32 78.62 1021.64 69.18
  Unit 3 210.0 3.75 3.71 3.97 72.43 79.84 1016.58 68.84
  Unit 4 210.0 3.87 3.73 4.04 76.70 84.55 1086.74 73.59
  Unit 5 210.0 3.80 3.80 4.25 74.56 82.19 1106.13 74.90
  Unit 6 210.0 3.66 3.69 4.21 71.93 79.29 1153.88 78.14
  Unit 7 500.0 8.13 8.67 9.20 163.45 75.67 2725.81 77.53
  Station 1760.0 26.92 27.31 29.67 530.39 69.76 8865.07 71.63
Rayalaseema Unit 1 210.0 3.79 3.76 3.96 60.81 67.03 932.71 63.16
  Unit 2 210.0     2.48 55.38 61.04 979.76 66.35
  Unit 3 210.0           711.31 48.17
  Unit 4 210.0 3.77 3.72 3.91 71.78 79.12 1013.44 68.63
  Unit 5 210.0     2.86 56.56 62.34 891.74 60.39
  Unit 6 600.0       21.96 8.47 544.28 12.90
  Station 1650.0 7.56 7.48 13.21 266.48 37.38 5073.24 43.72
APGENCO Thermal 3410.0 34.48 34.79 42.88 796.87 54.09 13938.31 58.13
Hydro Power Stations                  
Machkund (AP Utilisation) 84.0 0.81 0.80 0.83 15.78   228.70  
Tungabhadra (AP Utilisation) 57.6 0.33 0.25 0.22 6.04   81.75  
Upper Sileru 240.0 0.91 1.02 1.79 24.39   329.47  
Donkarayi 25.0 0.32 0.25 0.45 4.06   54.49  
Lower Sileru 460.0 2.60 3.08 4.01 60.31   801.15  
Srisailam Right 770.0       0.42   551.77  
NS Right Canal 90.0 0.17 0.23 0.17 6.19   97.56  
NS Tail Pond Dam   50.0           42.09  
Penna Ahobilam 20.0           1.43  
Chettipeta Mini Hydro 1.0           1.59  
APGENCO Hydro 1797.6 5.14 5.62 7.48 117.19   2190.00  
APGENCO Solar 5.4 0.02 0.02 0.02 0.78 33.36 6.62 17.36
APGENCO Total 5213.0 39.64 40.43 50.38 914.83   16134.93  
                   
Machkund (Total) 120.0 1.71 1.71 1.80 32.82   456.79  
Tungabhadra (Total) 72.0 0.44 0.33 0.30 8.29   117.00  
APPDCL                  
Total SDSTPS station 1600.0 22.79 23.65 13.89 161.57 23.38 5552.38 49.35
Outage of Thermal Units
Dr NTTPS 1 (210 MW) is under Reserve standby from 22:27 on 09.11.18 and overhaul works taken up from 00:00 on  03.01.2019
RTPP 3(210 MW) is under annual Overhaul from 23:00 on 08.11.18
RTPP 6 (600 MW) is under outage due to Ash evacuation problem from 23:27 on 03.01.19
RTPP 2(210 MW) is under Reserve standby from 14:48 on 15.01.19 to 06;24 on 18.01.19
RTPP 5 (210 MW) is under Reserve standby from 10:01 on 14.01.19 to 05;06 on 18.01.19
Outage of Hydro Units
Machkund 4 (23 MW) was under under shutdown due to rotar earth fault from 18:35 on 12.09.17
Machkund 3 (23 MW) was hand tripped due to sparks in main exciter at 00.00 on 08.01.2019
Outage of SDSTPS Units
SDSTPS 2 9800 MW) is under outage due to boiler tube leak from 00;33 on 18.01.19