ANDHRA PRADESH POWER GENERATION CORPORATION LIMITED
VIDYUT SOUDHA  ::  Vijayawada - 520004
Daywise Generation Particulars as on  :  12-11-2019
Station Unit Capacity Daywise generation in MU 1st to 12th Nov 1st Apr to 12th Nov
(MW) 10-11-19 11-11-19 12-11-19 Gen (MU) PLF (%) Gen (MU) PLF (%)
Thermal Power Stations                
Dr.Narla Tatarao Unit 1 210.0           740.68 65.03
(Vijayawada) Unit 2 210.0 3.95 3.92 3.95 47.99 79.35 771.64 67.74
  Unit 3 210.0 3.91 3.94 4.10 24.18 39.98 755.91 66.36
  Unit 4 210.0 3.96 3.96 4.20 49.33 81.56 825.26 72.45
  Unit 5 210.0 4.06 4.11 4.31 50.37 83.28 894.49 78.53
  Unit 6 210.0 3.88 3.94 4.16 50.85 84.08 857.81 75.31
  Unit 7 500.0   6.57 9.17 95.32 66.19 2024.53 74.65
  Station 1760.0 19.76 26.44 29.89 318.04 62.74 6870.32 71.97
Rayalaseema Unit 1 210.0           719.73 63.19
  Unit 2 210.0           431.51 37.88
  Unit 3 210.0 3.88 4.16 4.10 48.53 80.24 811.23 71.22
  Unit 4 210.0           776.88 68.20
  Unit 5 210.0           556.58 48.86
  Unit 6 600.0       67.24 38.91 1354.49 41.62
  Station 1650.0 3.88 4.16 4.10 115.77 24.36 4650.20 51.96
APGENCO Thermal 3410.0 23.64 30.60 33.99 433.81 44.17 11520.52 62.29
Hydro Power Stations                
Machkund (AP Utilisation) 84.0 1.03 1.05 1.02 10.31   209.85  
Tungabhadra (AP Utilisation) 57.6 0.80 0.97 0.71 10.23   76.38  
Upper Sileru 240.0 2.58 1.56 2.54 35.33   355.89  
Donkarayi 25.0       0.15   42.25  
Lower Sileru 460.0 0.79 0.33 0.31 6.82   476.49  
Srisailam Right 770.0 7.22 5.82 2.59 115.01   1070.56  
NS Right Canal 90.0 0.73 0.71 0.69 8.50   84.40  
NS Tail Pond Dam   50.0 1.08 1.11 1.12 12.83   74.10  
Penna Ahobilam 20.0              
Chettipeta Mini Hydro 1.0           1.02  
APGENCO Hydro 1797.6 14.23 11.54 8.98 199.18   2390.94  
 Solar pant at polavaram 5.4 0.02 0.02 0.03 0.28 18.08 4.71 16.02
Solar plant at Talaricheruvu 400.0 2.30 2.40 2.06 23.85 20.70 426.14 19.64
APGENCO Solar 405.4 2.32 2.43 2.09 24.13 20.66 430.86 19.59
APGENCO Total 5613.0 40.19 44.57 45.05 657.12   14342.32  
                   
Machkund (Total) 120.0 2.22 2.16 2.16 21.77   408.20  
Tungabhadra (Total) 72.0 1.03 0.99 0.92 11.77   103.07  
APPDCL                  
Total SDSTPS station 1600.0 25.70 24.20 24.25 195.12 42.34 4800.69 55.32
Outage of Thermal Units
RTPP 2 (210 MW) is under outage  due to coal shortage (flexi coal  scheme) from 12:00 on 19.09.19.
RTPP 1 (210 MW) is under Reserve shut down from 22:04 on 27.10.19.
RTPP 5 (210 MW) is under outage due to coal shortage (flexi coal scheme) from 21:27 on 16.10.19
Dr NTTPS 1 (210 MW) is under outage  for coal conservation  from 22:40 on 30.10.19
RTPP 4 (210 MW) is under annual Overhaul from 00:00 on 30.10.19
RTPP 6 (600 MW) is under outage due to Condenser tube leak from 12:19 on 08.11.19
Outage of Hydro Units
Machkund 2 (17 MW) is under outage from 09:00 on 10.09.19
LSL 1(115 MW) is under outage due to abnormal sounds and heavy vibration at PMG from 16:40 on 08.07.19
Outage of SDSTPS Units
Nil