ANDHRA PRADESH POWER GENERATION CORPORATION LIMITED
VIDYUT SOUDHA  ::  Vijayawada - 520004
Daywise Generation Particulars as on  :  20-03-2019
Station Unit Capacity Daywise generation in MU 1st to 20th Mar 1st Apr to 20th Mar
(MW) 18-03-19 19-03-19 20-03-19 Gen (MU) PLF (%) Gen (MU) PLF (%)
Thermal Power Stations                
Dr.Narla Tatarao Unit 1 210.0 3.89 4.08 4.02 81.27 80.63 946.90 53.07
(Vijayawada) Unit 2 210.0 3.90 4.01 3.98 80.16 79.52 1249.69 70.04
  Unit 3 210.0 3.96 4.02 4.08 81.53 80.88 1265.89 70.95
  Unit 4 210.0 4.02 4.11 4.17 83.18 82.52 1327.51 74.41
  Unit 5 210.0 3.99 4.26 4.13 85.28 84.60 1361.93 76.33
  Unit 6 210.0 4.04 4.26 4.04 85.10 84.42 1332.41 74.68
  Unit 7 500.0 9.61 10.29 11.53 120.87 50.36 3021.28 71.12
  Station 1760.0 33.41 35.03 35.95 617.39 73.08 10505.61 70.26
Rayalaseema Unit 1 210.0 3.68 3.94 4.07 77.63 77.01 1127.75 63.21
  Unit 2 210.0 1.49     66.21 65.69 1188.66 66.62
  Unit 3 210.0 3.67 4.00 4.01 82.38 81.72 839.09 47.03
  Unit 4 210.0       58.88 58.41 1235.86 69.27
  Unit 5 210.0       54.98 54.54 1026.89 57.56
  Unit 6 600.0 8.92 9.30 9.10 137.42 47.71 990.07 19.42
  Station 1650.0 17.76 17.24 17.18 477.49 60.29 6408.32 45.71
APGENCO Thermal 3410.0 51.17 52.27 53.13 1094.88 66.89 16913.93 58.38
Hydro Power Stations                  
Machkund (AP Utilisation) 84.0 0.79 0.82 0.82 16.48   286.74  
Tungabhadra (AP Utilisation) 57.6 0.18 0.25 0.07 4.57   96.04  
Upper Sileru 240.0 2.40 2.01 1.91 41.08   450.09  
Donkarayi 25.0 0.25 0.26 0.25 5.03   74.95  
Lower Sileru 460.0 3.13 4.46 4.23 79.60   1052.51  
Srisailam Right 770.0           552.02  
NS Right Canal 90.0           101.55  
NS Tail Pond Dam   50.0 0.39 0.36 0.39 3.37   47.96  
Penna Ahobilam 20.0           1.43  
Chettipeta Mini Hydro 1.0           2.03  
APGENCO Hydro 1797.6 7.14 8.16 7.67 150.11   2665.31  
 Solar pant at polavaram 5.4 0.03 0.03 0.03 0.52 20.13 7.74 16.80
Solar plant at Talaricheruvu 400.0 2.41 2.30 2.15 44.08 22.96 108.73  
APGENCO Solar 405.4 2.44 2.33 2.17 44.61   116.47
APGENCO Total 5613.0 60.76 62.75 62.97 1289.60   19695.71
                   
Machkund (Total) 120.0 1.67 1.67 1.67 35.50   575.37  
Tungabhadra (Total) 72.0 0.24 0.25 0.25 5.95   135.35  
APPDCL                  
Total SDSTPS station 1600.0 25.60 25.71 26.64 482.64 62.84 6635.31 48.81
Outage of Thermal Units
RTPP 4 (210 MW) is under Reserve shut down from 23:42 on 14.03.19
RTPP 5 (210 MW) is under Reserve shut down from 12:26 on 14.03.19
RTPP 2 (210 MW) is under reserve shut down from 09:47 on 18.03.19
Outage of Hydro Units
Machkund 4 (23 MW) was under under shutdown due to rotar earth fault from 18:35 on 12.09.17
USL 1 (60 MW) is under outage due to servomotor vibrations from  on 15:00 on 14.02.19
Machkund 3 (17 MW) was under under shutdown due to commutator  brush sparks from 21:35 13.03.19
LSL (115 MW) is under outage due to turbine side problem from 12:15 on 05.03.19
Outage of SDSTPS Units
Nil